Client: CBRE

Description: A commercial office building in Weybridge, requiring a replacement air cooled water chiller.

The chiller replacement contract was carried out in 2014, and comprised the removal of the existing Trane air cooled chiller, two chilled water pumps and the chilled water pressurization unit and expansion vessel.

The existing chiller was de-commissioned and removed from the roof. The new Aermec chiller was lifted in to position and mounted on galvanised steel beams complete with anti vibration mountings.

New inverter pumps were selected and installed, along with a new pressure step de-gasser and a refrigerant gas detection system.

The 150kW unit was installed with minimal downtime (a weekend), by pre-fabricating sections of pipework and pre-installing power cables, ready for connection.